The Azuro Energy Oil Production Optimization System (OPOS) has proven to work.


Three (3) case studies are shown to highlight the impact of the Azuro solution.


  BEFORE Oil Production
(barrels/day)
AFTER Oil Production
(barrels/day)
(*) Monthly Increase
(USD)
Case Study 1 10.7 19.5 $18,480
Case Study 2 26.4 39.6 $27,720
Case Study 3 76 154.5 $164,850

(*) Based on $70US/barrel


Case Study 1: Revenue increase of $18,480/month

Before After

• Casing Pressure @ 150 PSIG

• 1.7 m3/d [10.7 bbl/d] Oil

• 2.5 m3/d [15.7 bbl/d] H20

• 1.2 e3m3/d [42.6mcf/d] Gas

• Pumped Off

• Casing Pressure @ 10 PSIG

• 3.1 m3/d [19.5 bbl/d] Oil

• 3.3 m3/d [20.7 bbl/d] H20

• 1.7 e3m3/d [60.3mcf/d] Gas


Case Study 2: Revenue increase of $27,720/month

Before After

• Casing Pressure @ 190 PSIG

• 8 Joints of Fluid above pump

• 4.2 m3/d [26.4.7 bbl/d] Oil

• 110 m3/d [691 bbl/d] H20

• 1.5 e3m3/d [53.25mcf/d] Gas

• Casing Pressure @ 15 PSIG

• 25 Joints of Fluid above pump

• 6.3 m3/d [39.6 bbl/d] Oil

• 120 m3/d [753.6 bbl/d] H20

• 1.7 e3m3/d [60.3mcf/d] Gas


Case Study 3: Revenue increase of $164,850/month

Before After After Pump Change/Repair

• Casing Pressure @ 125 PSIG

• 5 Joints of Fluid above pump

• 12.1 m3/d [76 bbl/d] Oil

• 3.6 m3/d [22.6 bbl/d] H20

• 3.4 e3m3/d [120.7mcf/d] Gas

• Casing Pressure @ 20 PSIG

• 65 Joints of Fluid above pump

• 12.5 m3/d [78.5 bbl/d] Oil

• 3.6 m3/d [22.6 bbl/d] H20

• 4.5 e3m3/d [160 mcf/d] Gas

• Casing Pressure @ 10 PSIG

• 12 Joints of Fluid above pump

• 24.6 m3/d [154.5 bbl/d] Oil

• 7.9 m3/d [49.6 bbl/d] H20

• 4.9 e3m3/d [174 mcf/d] Gas