The Azuro Energy Oil Production Optimization System (OPOS) has proven to work.
Three (3) case studies are shown to highlight the impact of the Azuro solution.
| BEFORE Oil Production (barrels/day) |
AFTER Oil Production (barrels/day) |
(*) Monthly Increase (USD) |
|
| Case Study 1 | 10.7 | 19.5 | $18,480 |
| Case Study 2 | 26.4 | 39.6 | $27,720 |
| Case Study 3 | 76 | 154.5 | $164,850 |
(*) Based on $70US/barrel
| Before | After |
|
• Casing Pressure @ 150 PSIG • 1.7 m3/d [10.7 bbl/d] Oil • 2.5 m3/d [15.7 bbl/d] H20 • 1.2 e3m3/d [42.6mcf/d] Gas • Pumped Off |
• Casing Pressure @ 10 PSIG • 3.1 m3/d [19.5 bbl/d] Oil • 3.3 m3/d [20.7 bbl/d] H20 • 1.7 e3m3/d [60.3mcf/d] Gas |
| Before | After |
|
• Casing Pressure @ 190 PSIG • 8 Joints of Fluid above pump • 4.2 m3/d [26.4.7 bbl/d] Oil • 110 m3/d [691 bbl/d] H20 • 1.5 e3m3/d [53.25mcf/d] Gas |
• Casing Pressure @ 15 PSIG • 25 Joints of Fluid above pump • 6.3 m3/d [39.6 bbl/d] Oil • 120 m3/d [753.6 bbl/d] H20 • 1.7 e3m3/d [60.3mcf/d] Gas |
| Before | After | After Pump Change/Repair |
|
• Casing Pressure @ 125 PSIG • 5 Joints of Fluid above pump • 12.1 m3/d [76 bbl/d] Oil • 3.6 m3/d [22.6 bbl/d] H20 • 3.4 e3m3/d [120.7mcf/d] Gas |
• Casing Pressure @ 20 PSIG • 65 Joints of Fluid above pump • 12.5 m3/d [78.5 bbl/d] Oil • 3.6 m3/d [22.6 bbl/d] H20 • 4.5 e3m3/d [160 mcf/d] Gas |
• Casing Pressure @ 10 PSIG • 12 Joints of Fluid above pump • 24.6 m3/d [154.5 bbl/d] Oil • 7.9 m3/d [49.6 bbl/d] H20 • 4.9 e3m3/d [174 mcf/d] Gas |
Contact us for more information.